Friday, May 16, 2014


During the next two weeks, the roadway contractor will be working on installing curb and gutter, and pavement. The underground crew will also be working on storm sewer for the next three weeks.  The electrical subcontractor is scheduled to be installing concrete foundations and electrical conduit for the new traffic signals.
 
Contractor's typical working hours are 7 AM to 3:30 PM and all of the construction activities will be contained within the traffic lane closure areas.