Friday, June 6, 2014

Next week and the following week the roadway contractor will continue working on installing curb and gutter, and pavement. The underground crew will also be working on storm sewer for the next two weeks.  The electrical subcontractor is scheduled to continue installing concrete foundations and electrical conduit for the new traffic signals.
Contractor's typical working hours are 7 AM to 3:30 PM and all of the construction activities will be contained within the traffic lane closure areas.