Friday, July 11, 2014

No change to the traffic pattern is expected for the next two weeks.  However, during the week of July 28th there is a major change to the traffic patterned scheduled, which will shift traffic to the outside lanes.  Next week and the following week the roadway contractor will continue working on installing curb and gutter, and pavement. The electrical subcontractor is scheduled to continue installing concrete foundations and electrical conduit for the new traffic signals.
Contractor's typical working hours are 7 AM to 3:30 PM and all of the construction activities will be contained within the traffic lane closure areas.