Monday, August 4, 2014


Starting Friday, Aug 1st, between 10 AM and noon, a new traffic pattern was created to start the road work for stage II. Per plan, we will have the inside lane on each leg of the intersection closed and this is a long term closure. During this stage, we will maintain two lanes for through traffic, a right turn lane, and one left lane in each direction on Golf Rd. On Waukegan Rd, we will keep one lane for through traffic, a right turn lane, and one left lane in each direction.

During the next two weeks the roadway contractor will be removing and replacing curb and gutter and pavement with the new alignment. The electrical contractor will be placing new  traffic signals at intersections.